APSC JE Civil Engineering 2021 PYQ with Answers । Part - 6

Civil Engineering MCQ Quiz

51 The unit of measurement of concrete work in RCC is

  • [A] square meter
  • [B] cubic meter
  • [C] quintal
  • [D] running meter

Correct Answer is: [B] cubic meter

52 Which of the following is the most accurate estimate?

  • [A] Plinth area estimate
  • [B] Cube rate estimate
  • [C] Detailed estimate
  • [D] Building cost index estimate

Correct Answer is: [C] Detailed estimate

53 The volume of coarse aggregates (CA) required to make 100 m³ of M-15 concrete is

  • [A] 85 m³
  • [B] 100 m³
  • [C] 95 m³
  • [D] 88 m³

Correct Answer is: [D] 88 m³

54 If B is the width of formation, d is the height of embankment, side slope s:1 for a highway with no transverse slope, then the area of cross-section is

  • [A] B+d+sid
  • [B] B d+s d²
  • [C] B(d-s²)
  • [D] 0.5(Bd+s d²)

Correct Answer is: [B] B d + s d²

55 The damp-proof course is measured in

  • [A] cubic meter
  • [B] square meter
  • [C] meters
  • [D] None of the above

Correct Answer is: [B] square meter

56 PERT stands for

  • [A] Programme Estimation and Reporting Technique
  • [B] Process Estimation and Review Technique
  • [C] Programme Evaluation and Review Technique
  • [D] Planning Estimation and Resulting Technique

Correct Answer is: [C] Programme Evaluation and Review Technique

57 The performance of a specific task in CPM is known as

  • [A] dummy
  • [B] activity
  • [C] event
  • [D] contract

Correct Answer is: [B] activity

58 The technique for establishing and maintaining priorities among the various jobs of a project is known as

  • [A] event flow scheduling technique
  • [B] critical ratio scheduling
  • [C] slotting technique for scheduling
  • [D] short interval scheduling

Correct Answer is: [B] critical ratio scheduling

59 The difference between the time available to do the job and time required to do the job is known as

  • [A] event
  • [B] float
  • [C] duration
  • [D] constraint

Correct Answer is: [B] float

60 Black cotton soil is mainly

  • [A] clayey soil
  • [B] sandy soil
  • [C] cohesionless soil
  • [D] silty

Correct Answer is: [A] clayey soil

Questions Completed!
Your Score:
0/10